Eiger Funding v Ridge and Partners: TCC finds monitoring surveyor liable for negligent advice to funder

In Eiger Funding (PCC) Limited v Ridge and Partners LLP, the Technology and Construction Court (“TCC”) held that an independent monitoring surveyor was liable for advice given to a lender in connection with a failed development project.

The judgment provides important guidance on the duties owed by monitoring surveyors in development finance transactions. Notably, it is understood to be the first case in which liability has been established, in part, due to a failure to properly manage a conflict of interest in breach of RICS guidance, where the surveyor also acted for the developer.

The facts

In 2018, Signature Living Residential Ltd (“Signature”) obtained a £12.9 million loan from Eiger Funding (PCC) Limited (“Eiger”) to finance the conversion of an existing building in Liverpool into 122 residential flats (the “Project”).

Eiger appointed Ridge and Partners LLP (“Ridge”) as its independent monitoring surveyor. Ridge had previously acted for Signature as quantity surveyor on the same project.

Ridge prepared a monitoring surveyor’s report, which Eiger relied upon in deciding to approve the loan. The loan was subsequently advanced.

The Project encountered significant difficulties and made poor progress. In 2020, the relevant Signature companies entered administration. Eiger ultimately suffered losses of approximately £10.8 million under the loan.

Eiger brought a claim in professional negligence against Ridge, contending that it would not have entered into the loan had Ridge properly performed its duties.

The issues

Eiger advanced four principal arguments:

  1. Conflict of interest – Ridge acted both for Signature (as quantity surveyor) and Eiger (as monitoring surveyor) without obtaining Eiger’s informed consent, contrary to RICS guidance.

  2. Inadequate contract sum – Ridge failed to advise that the contract sum was unrealistically low and created a material risk of contractor failure and/or cost overruns.

  3. Lack of independent cost assessment – Ridge did not provide an independent estimate of the cost to complete, instead adopting figures provided by the developer without adequate scrutiny.

  4. Failure to identify structural risks – Ridge did not advise on the close relationship between Signature and its contractor, which introduced risks in relation to cost control and programme.

Ridge disputed liability, including whether it owed Eiger a duty of care in tort and/or contract, and denied any breach.

The decision

Duty of care

The Court held that Ridge did owe Eiger a duty of care. The purpose of a monitoring surveyor’s appointment is to provide an independent and professional assessment of a development before (and during) the advancement of funds.

That duty required Ridge to:

  • Assess the adequacy of the contract sum;

  • Identify and report material risks (including cost overruns and programme delays);

  • Critically evaluate the developer’s assumptions; and

  • Provide a genuinely independent view of the likely cost to complete the development.

Breach

Ridge was found to be in breach of its duty on multiple grounds:

  • Failure to challenge cost assumptions - Ridge did not advise that there was a substantial risk that actual build costs would significantly exceed the developer’s figures.

  • Change in procurement model - Ridge failed to highlight that the building contract had moved from a fixed-price arrangement to a target cost contract, effectively transferring cost overrun risk away from the contractor.

  • Reliance on inadequate data - Ridge adopted cost figures without sufficient independent verification.

  • Failure to flag relationships and risks - Ridge did not adequately advise on the relationship between the developer and contractor.

Conflict of interest

A key aspect of the judgment was Ridge’s failure to manage its conflict of interest.

The Court found that Ridge had prepared earlier cost estimates in its role as the developer’s quantity surveyor, which it did not properly disclose or manage when acting for Eiger, and it failed to obtain fully informed consent in accordance with RICS guidance.

The judge observed that Ridge was effectively “marking its own homework.”

Ridge also failed to update Eiger adequately on significant cost inflation (approximately 20%) since its earlier estimates.

Causation and loss

Crucially, the Court limited the scope of recoverable loss.

The risk Ridge had a duty to guard against was entering into a loan based on inaccurate construction cost advice, not the entirety of the project failing.

Ridge had advised that the cost to complete would be approximately £2.9 million. The Court found the true figure to be approximately £5.4 million. Damages were therefore assessed at £2.5 million, representing the difference between those figures — rather than Eiger’s full losses on the loan.

Comments

This is a significant TCC decision on the liability of monitoring surveyors.

Key takeaways include:

  • Independent judgment is critical - Monitoring surveyors must critically analyse and verify information, rather than rely on developer-provided figures.

  • Conflicts must be rigorously managed - Compliance with RICS guidance is essential. Simply disclosing a conflict is not enough. Informed consent must be properly obtained and documented.

  • Scope of liability may be limited - The decision reinforces that professionals are liable only for losses falling within the scope of the duty breached, not all downstream losses.

  • Heightened scrutiny of dual roles - Acting for both developer and lender will attract close judicial scrutiny and carries clear risk.

If you would like further information or advice in relation to a construction dispute, please contact a member of our Construction team.